The U.S. Army Corps of Engineers' change-of-ownership application says the existing Shoreline Use Permit expires when lakefront property changes hands. The application asks for a recorded deed, and an Area Ranger inspects the shoreline against the Corps' 2004 Shoreline Management Plan.

The permit belongs to the parcel, and it ends with the owner

The Corps' change-of-ownership application, posted in October 2026, says the permit is tied to the tax parcel identification number, not to the owner. When private property changes ownership, the permit expires and the new owners "must apply for a new permit in their name." The 2004 Lake Lanier Shoreline Management Plan says the same in stronger terms. Permits are nontransferable, become void on sale or transfer, and run no longer than five years. A permit also does not grant real estate rights or exclusive use of government land.

The last point shapes everything else. The strip between a lakefront lot and the water is generally public land managed by the Corps.

The change-of-ownership paperwork

The Corps' change-of-ownership application asks for these documents together:

  1. A recorded deed. It must show the county recording stamp, a notary stamp and signature, the grantor's signature and the full legal description, usually labeled "Exhibit A." The Corps says it cannot accept closing statements or security deeds.
  2. A current survey or plat. It must show property lines and measurements, existing structures and the lot number or address. In most cases the Corps cannot accept subdivision plats, county GIS maps or satellite images, including Google Maps.
  3. A scaled drawing of the existing dock. It must give overall length and width, slip dimensions, walkway and gangway widths, and roof dimensions and overhang if there is a roof. Photos can support the drawing but cannot replace it.
  4. A site drawing. It must show the Corps property line, the private property lines, the shoreline bank, the path to the dock, neighboring docks and the dock's authorized location.
  5. A proposed dock drawing, if the new owner wants changes.

On the Permit Program page, the Corps estimates about 6 to 8 weeks to evaluate and process a completed package. The application lists the usual reasons for delay: a missing deed with a legal description, survey, measured dock drawing, site drawing or access information.

Item four is the one buyers and sellers tend to miss. The Corps asks for the dock's authorized location and notes that it "may be different from where the dock is currently located." A dock can drift, get moved or get rebuilt over the years.

What the ranger compares against the plan

After a complete package arrives, an Area Ranger reviews it and inspects the shoreline to "verify existing shoreline facilities and determine whether the property adheres to the 2004 Shoreline Management Plan." The Corps' Shoreline Management page still links the 2004 plan as the governing document. Several provisions in that plan can change what a buyer actually keeps.

What a showing may suggest What the 2004 SMP and Corps rules say
The lawn runs to the water Mowing on public land is prohibited unless a permit authorizes an existing grassy area. Mowing areas are to be minimized during ownership changes, and previously authorized areas may not be renewed where woody vegetation has grown back.
The view was opened up Only limited understory removal is allowed, under specified conditions. Clearing for a view or a lawn is not permitted.
The waterline marks the lot line Private property lines do not extend onto public land. Most Corps boundaries are straight lines between surveyed points, so the 1,071-foot full-pool shoreline is not, by itself, the government boundary.
The dock has been updated Changes from approved dock plans require prior written approval.
There is a bench and storage by the water Unpermitted items on public land, such as swings, picnic tables, benches, storage sheds and boat trailers, are prohibited.

Older structures carry their own condition. The Corps' Permit Program page lists grandfathered items, including boat ramps, shoreline access roads, marine rails, patios, pumphouses, wells, picnic shelters, hand rails and land-based boathouses. For each, new authorizations are not permitted, and removal is required when the facility becomes unsafe or unusable. The plan also says no new authorizations will be granted for fixed piers, because they block access at low lake levels.

The plan allows periodic inspections and requires deficiencies to be corrected. The Permit Program page notes that violations of the federal regulations governing Lake Lanier, found in 36 CFR Part 327, can bring a fine of up to $5,000, up to six months of imprisonment, restoration of damages or permit revocation.

The electrical letter changed on October 1, and its wording changes again January 1

The electrical service to a dock is reviewed at every change of ownership. Under the 2004 plan, all service on public land must have ground-fault protection and be buried underground, whatever its age or grandfathered status. Recertification is required at each renewal and each change of ownership.

On September 21, 2026, the Corps' Mobile District announced an administrative change to how that certification is documented. The release says the electrical requirements themselves are not changing. Only the paperwork is. A separate Corps document with the revised plan language sets a second date.

Timing What the Corps documents say
Packages mailed before Oct. 1, 2026 Processed with Exhibit C, the form signed by a state-licensed electrical contractor.
Beginning Oct. 1, 2026 Exhibit C is removed from renewal, modification and change-of-ownership packages and replaced by a letter from a state-licensed electrical contractor certifying compliance with current National Electrical Code requirements.
Effective Jan. 1, 2027 The revised SMP section requires an original letter no more than three months old. It must list the Corps permit or license number, the electrical components inspected, the contractor's printed name and signature, the Georgia electrical contractor's license number and the inspection date.

The January text also spells out physical details. Service serving private docks must meet Article 555 of the current NEC, and the line from the government property line must follow the access path. Unless the NEC requires otherwise, the service pole must be pressure-treated 6-by-6 wood no more than 8 feet above the ground, with one pole per dock.

The 2004 plan is still the rulebook

Revisions are under discussion. The Lake Lanier Association's Winter/Spring 2026 newsletter reported results from its member survey on the Shoreline Management Plan. Roughly 220 comments concerned dock boxes alone. The association said it would propose revising the Dock Box section and would present a report to the Corps, starting with the Buford project office. These are recommendations, not adopted rules. Until the Corps adopts a new plan, a change-of-ownership inspection is measured against the 2004 document and approved administrative changes such as the electrical revision.

Questions buyers and sellers ask

What does the change-of-ownership fee cost? The Corps' Permit Program page lists an administrative fee for "New Permit / Change of Ownership" but does not publish an amount, and it says rates are subject to change. The Shoreline Help Desk at 770-904-3262 can give the current figure.

Where does the application go? By email as PDF attachments to [email protected], or by mail or in person at the Lake Lanier Project Management Office, 1050 Buford Dam Road, Buford, GA 30518. The office is open Monday through Friday, 8 a.m. to 3:30 p.m.

Can a new owner request dock changes in the same application? Yes. The application has a section for special requests, and changes must be submitted with the application along with a separate drawing of the proposed work. The Permit Program page also notes a limit on how many permits can be issued for the lake at one time, with a wait-list when none are available. How that limit affects a particular request is a question for the Area Ranger.

This post is general information about published Corps rules, not legal advice. Shoreline and contract questions for a specific property should be confirmed with the Corps and the appropriate attorney or professional.